Healthcare Realty and Harker Construction are making steady progress toward the redevelopment of the common areas at Huntersville Office Park V.
Here’s what’s happening now:
Week of October 7 – 11
Floor 1 | Water fountain demolition begins |
Floor 2 | Balcony concrete demolition begins Water fountain installation begins |
Floor 3 | Wall baffle installation begins |
Week of October 14 – 18
Floor 1 | Tile demolition and installation begins Ceiling sheetrock installation begins |
Floor 2 | Wall baffle installation begins |
Floor 3 | Glass entry installation continues Installation of restroom partitions continues Installation of restroom fixtures begins |
Updated: June 21, 2024
Healthcare Realty is about to begin the next phase of our $5 million redevelopment project at Huntersville Office Park V.
Having completed the Floor 3 improvements, work will begin Monday, July 1, on the corridors and other common areas of Floor 2. The work on Floor 2 will continue for approximately five weeks, as we install all-new flooring, walls, ceilings, and lighting, giving your workplace a fresh, modern look. The Floor 2 improvements will be completed in zones, with each successive zone finished before the next one begins.
To minimize disruption to tenants and patients during this time, we have scheduled most of the work to take place outside of our tenants’ regular business hours. During the day, protective taping and signage will be in place advising patients and visitors to use caution around construction areas.
Our contractors will clean the construction area thoroughly when they conclude their work each night. Healthcare Realty team members will conduct daily inspections to ensure impacts to tenants and visitors are as limited as possible.
We expect to finish the improvements to the Floor 2 corridors by approximately mid-August. At that point, we will begin the lobby and restroom renovations. We will provide additional updates to tenants once that phase of the work has been definitively scheduled, including expected dates of restroom closures.
Healthcare Realty is committed to investing in our buildings to create long-term value for our tenants and an improved visitor experience for patients. We appreciate your understanding during the construction process and look forward to the difference the planned updates will bring to the building!
If you have any questions or concerns, please contact the Management Office.
Renderings
Here’s a look at the planned updates to the Floor 2 corridors.